"B" Gas Plant Vessels Replacement look back at PT. XYZ
Purpose – The look back evaluates the project performance of “B” Gas Plant Vessels Replacement that successful to be installed on site with plus and minus following result: • Operational Excellence / HES Compliance: no Motor Vehicle Crash (MVC), no Total Recordable Incidents (TRI), no Spill, and ze...
Saved in:
Main Author: | |
---|---|
Format: | Conference or Workshop Item |
Language: | English |
Published: |
2014
|
Subjects: | |
Online Access: | http://repo.uum.edu.my/15959/1/P36.pdf http://repo.uum.edu.my/15959/ http://stmlportal.net/ictom04/TOC.html |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | Purpose – The look back evaluates the project performance of “B” Gas Plant Vessels Replacement
that successful to be installed on site with plus and minus following result: • Operational Excellence / HES Compliance: no Motor Vehicle Crash (MVC), no Total Recordable Incidents (TRI), no Spill, and zero accident related to H2S emission.• Reliability: zero downtime due to corrosion at compression system.• Budget compliance: the total spending is still within budget, about 63% of the total original
budget.• Schedule: delay in construction execution.Design/Methodology/Approach – Major deviations of the project performance are investigated by using Root Cause Analysis (RCA).
Findings – Based on the RCA, it’s found the critical items need to be improved for the future project.Research limitations / implications – This paper is intended as learning for college students, some data are not included in this paper due to company confidential. Original/Value – To present an original approach of look back that modelled after incident investigation system. |
---|