Time Delay and Cost Overrun of Road over Bridge (ROB) Construction Projects in India

This paper aims at studying the factors that contribute to time delay and cost overrun of Road over Bridge (ROB) projects in India. Data for the research study were collected from 62 respondents, including owners, contractors, and consultants of ROB projects. The literature survey and the questio...