The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin

An analytical approach for explaining the variability in labour intensive construction operations has been developed. Data has been collected daily from 3 sites. Not only productivity but many of the factors affecting it have been measured. The quantification of the impact of each individual factor...

Full description

Saved in:
Bibliographic Details
Main Author: Hussin, Alias
Format: Thesis
Language:English
Published: 1990
Subjects:
Online Access:https://ir.uitm.edu.my/id/eprint/99618/1/99618.pdf
https://ir.uitm.edu.my/id/eprint/99618/
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.uitm.ir.99618
record_format eprints
spelling my.uitm.ir.996182024-09-12T03:15:21Z https://ir.uitm.edu.my/id/eprint/99618/ The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin Hussin, Alias Materials of engineering and construction An analytical approach for explaining the variability in labour intensive construction operations has been developed. Data has been collected daily from 3 sites. Not only productivity but many of the factors affecting it have been measured. The quantification of the impact of each individual factor is based on the assumption that deviations from an operative's normal output arise because of disturbances imposed by a multiplicity of site factors. The impact of each individual factor causes the average daily productivity to change. Analysis of variance has been used to study the influence of the following variables on productivity of concrete casting. Cause of delay length of delay length of workday gang composition height of work area The objective of the research is to determine the productivity index (labour constant) and to identify factors which affect productivity. The ultimate use of productivity measurement is that of project control. 1990 Thesis NonPeerReviewed text en https://ir.uitm.edu.my/id/eprint/99618/1/99618.pdf The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin. (1990) Advanced Diploma thesis, thesis, Universiti Teknologi MARA (UiTM). <http://terminalib.uitm.edu.my/99618.pdf>
institution Universiti Teknologi Mara
building Tun Abdul Razak Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Mara
content_source UiTM Institutional Repository
url_provider http://ir.uitm.edu.my/
language English
topic Materials of engineering and construction
spellingShingle Materials of engineering and construction
Hussin, Alias
The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
description An analytical approach for explaining the variability in labour intensive construction operations has been developed. Data has been collected daily from 3 sites. Not only productivity but many of the factors affecting it have been measured. The quantification of the impact of each individual factor is based on the assumption that deviations from an operative's normal output arise because of disturbances imposed by a multiplicity of site factors. The impact of each individual factor causes the average daily productivity to change. Analysis of variance has been used to study the influence of the following variables on productivity of concrete casting. Cause of delay length of delay length of workday gang composition height of work area The objective of the research is to determine the productivity index (labour constant) and to identify factors which affect productivity. The ultimate use of productivity measurement is that of project control.
format Thesis
author Hussin, Alias
author_facet Hussin, Alias
author_sort Hussin, Alias
title The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
title_short The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
title_full The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
title_fullStr The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
title_full_unstemmed The determination of labour constant (productivity index) for construction process concreting works / Alias Hussin
title_sort determination of labour constant (productivity index) for construction process concreting works / alias hussin
publishDate 1990
url https://ir.uitm.edu.my/id/eprint/99618/1/99618.pdf
https://ir.uitm.edu.my/id/eprint/99618/
_version_ 1811598116624793600
score 13.211869