Recovery of damages beyond the limit of unenforceable liquidated damages clause

Standard forms of construction contracts typically include a liquidated damages provision entitling the employer a specified sum if the contractor is late in completing a work. However, such clause can be unenforceable due to a myriad of reasons, such as when time is at large. If that happens, the e...

Full description

Saved in:
Bibliographic Details
Main Author: Zainudin, Zulhilmi
Format: Thesis
Language:English
Published: 2017
Subjects:
Online Access:http://eprints.utm.my/id/eprint/87198/1/ZulhilmiZainuddinMFAB2017.pdf
http://eprints.utm.my/id/eprint/87198/
http://dms.library.utm.my:8080/vital/access/manager/Repository/vital:132588
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.utm.87198
record_format eprints
spelling my.utm.871982020-11-30T09:00:43Z http://eprints.utm.my/id/eprint/87198/ Recovery of damages beyond the limit of unenforceable liquidated damages clause Zainudin, Zulhilmi TH Building construction Standard forms of construction contracts typically include a liquidated damages provision entitling the employer a specified sum if the contractor is late in completing a work. However, such clause can be unenforceable due to a myriad of reasons, such as when time is at large. If that happens, the employer could not claim liquidated damages but may claim unliquidated damages instead. The issue is then whether the employer may claim unliquidated damages exceeding the sum specified in the liquidated damages provision although the clause is held to be unenforceable. The methodology utilized in this research is mainly through documentary analysis of court rulings. Six cases were shortlisted for analysis based on their relevance to the issue. The findings show that liquidated damages sum in construction contracts is always intended to cap the contractor’s liability for delay, thus, the employer may not recover more than the stipulated sum if the sum represents the parties’ intention even when the liquidated damages clause is unenforceable. 2017 Thesis NonPeerReviewed application/pdf en http://eprints.utm.my/id/eprint/87198/1/ZulhilmiZainuddinMFAB2017.pdf Zainudin, Zulhilmi (2017) Recovery of damages beyond the limit of unenforceable liquidated damages clause. Masters thesis, Universiti Teknologi Malaysia, Faculty of Built Environment. http://dms.library.utm.my:8080/vital/access/manager/Repository/vital:132588
institution Universiti Teknologi Malaysia
building UTM Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Malaysia
content_source UTM Institutional Repository
url_provider http://eprints.utm.my/
language English
topic TH Building construction
spellingShingle TH Building construction
Zainudin, Zulhilmi
Recovery of damages beyond the limit of unenforceable liquidated damages clause
description Standard forms of construction contracts typically include a liquidated damages provision entitling the employer a specified sum if the contractor is late in completing a work. However, such clause can be unenforceable due to a myriad of reasons, such as when time is at large. If that happens, the employer could not claim liquidated damages but may claim unliquidated damages instead. The issue is then whether the employer may claim unliquidated damages exceeding the sum specified in the liquidated damages provision although the clause is held to be unenforceable. The methodology utilized in this research is mainly through documentary analysis of court rulings. Six cases were shortlisted for analysis based on their relevance to the issue. The findings show that liquidated damages sum in construction contracts is always intended to cap the contractor’s liability for delay, thus, the employer may not recover more than the stipulated sum if the sum represents the parties’ intention even when the liquidated damages clause is unenforceable.
format Thesis
author Zainudin, Zulhilmi
author_facet Zainudin, Zulhilmi
author_sort Zainudin, Zulhilmi
title Recovery of damages beyond the limit of unenforceable liquidated damages clause
title_short Recovery of damages beyond the limit of unenforceable liquidated damages clause
title_full Recovery of damages beyond the limit of unenforceable liquidated damages clause
title_fullStr Recovery of damages beyond the limit of unenforceable liquidated damages clause
title_full_unstemmed Recovery of damages beyond the limit of unenforceable liquidated damages clause
title_sort recovery of damages beyond the limit of unenforceable liquidated damages clause
publishDate 2017
url http://eprints.utm.my/id/eprint/87198/1/ZulhilmiZainuddinMFAB2017.pdf
http://eprints.utm.my/id/eprint/87198/
http://dms.library.utm.my:8080/vital/access/manager/Repository/vital:132588
_version_ 1685578942715527168
score 13.164666