A risk-based project schedule estimation method to improve project reliability

This paper proposes a reliable project scheduling approach, which integrates the risk management and critical chain schedule analyses. Since various risks and uncertainties exist in a project which may not only prevent the project to be completed within budget and time limit, but also threaten the q...

Full description

Saved in:
Bibliographic Details
Main Authors: Mansoorzadeh, Shiva, Mohd. Yusof, Sha'ri, Zeynal, Hossein, Mansoorzadeh, Shahriar
Format: Article
Published: American Scientific Publishers 2012
Subjects:
Online Access:http://eprints.utm.my/id/eprint/32846/
http://dx.doi.org/10.1166/asl.2012.3830
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.utm.32846
record_format eprints
spelling my.utm.328462018-11-30T06:31:26Z http://eprints.utm.my/id/eprint/32846/ A risk-based project schedule estimation method to improve project reliability Mansoorzadeh, Shiva Mohd. Yusof, Sha'ri Zeynal, Hossein Mansoorzadeh, Shahriar TJ Mechanical engineering and machinery This paper proposes a reliable project scheduling approach, which integrates the risk management and critical chain schedule analyses. Since various risks and uncertainties exist in a project which may not only prevent the project to be completed within budget and time limit, but also threaten the quality, safety and operational needs. In the proposed method the potential project risks are taken into account and risk response strategies are developed by fuzzy failure mode and effect analysis (FMEA) and then varying effects of each risk over each activity. The project total time can then be quantified and simulated by Monte Carlo simulation (MCS) as an effective technique in uncertain conditions due to its capability of converting uncertainty to risk judgmentally in projects. Following this procedure fault tree analysis and event tree analysis will be used to get risk mitigations. Eventually, for a reliable schedule we distribute a critical chain schedule which allows one to implement the project as planned and obtain reasonable feeding buffer time and project buffer time. American Scientific Publishers 2012-06 Article PeerReviewed Mansoorzadeh, Shiva and Mohd. Yusof, Sha'ri and Zeynal, Hossein and Mansoorzadeh, Shahriar (2012) A risk-based project schedule estimation method to improve project reliability. Advanced Science Letters, 13 (1). pp. 813-816. ISSN 1936-6612 http://dx.doi.org/10.1166/asl.2012.3830 DOI:10.1166/asl.2012.3830
institution Universiti Teknologi Malaysia
building UTM Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Teknologi Malaysia
content_source UTM Institutional Repository
url_provider http://eprints.utm.my/
topic TJ Mechanical engineering and machinery
spellingShingle TJ Mechanical engineering and machinery
Mansoorzadeh, Shiva
Mohd. Yusof, Sha'ri
Zeynal, Hossein
Mansoorzadeh, Shahriar
A risk-based project schedule estimation method to improve project reliability
description This paper proposes a reliable project scheduling approach, which integrates the risk management and critical chain schedule analyses. Since various risks and uncertainties exist in a project which may not only prevent the project to be completed within budget and time limit, but also threaten the quality, safety and operational needs. In the proposed method the potential project risks are taken into account and risk response strategies are developed by fuzzy failure mode and effect analysis (FMEA) and then varying effects of each risk over each activity. The project total time can then be quantified and simulated by Monte Carlo simulation (MCS) as an effective technique in uncertain conditions due to its capability of converting uncertainty to risk judgmentally in projects. Following this procedure fault tree analysis and event tree analysis will be used to get risk mitigations. Eventually, for a reliable schedule we distribute a critical chain schedule which allows one to implement the project as planned and obtain reasonable feeding buffer time and project buffer time.
format Article
author Mansoorzadeh, Shiva
Mohd. Yusof, Sha'ri
Zeynal, Hossein
Mansoorzadeh, Shahriar
author_facet Mansoorzadeh, Shiva
Mohd. Yusof, Sha'ri
Zeynal, Hossein
Mansoorzadeh, Shahriar
author_sort Mansoorzadeh, Shiva
title A risk-based project schedule estimation method to improve project reliability
title_short A risk-based project schedule estimation method to improve project reliability
title_full A risk-based project schedule estimation method to improve project reliability
title_fullStr A risk-based project schedule estimation method to improve project reliability
title_full_unstemmed A risk-based project schedule estimation method to improve project reliability
title_sort risk-based project schedule estimation method to improve project reliability
publisher American Scientific Publishers
publishDate 2012
url http://eprints.utm.my/id/eprint/32846/
http://dx.doi.org/10.1166/asl.2012.3830
_version_ 1643649158162153472
score 13.18916