Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability

This project presents a methodological approach, suggestions and information in uprating the existing 275kV transmission overhead line. The work also calculate and analyses the effect of conductor swing angle on L3 tower top geometrics and keep the probability of flashover at low state. In thi...

Full description

Saved in:
Bibliographic Details
Main Author: Mat Yamin, Mohd Khairuddin
Format: Thesis
Language:English
English
English
Published: 2012
Subjects:
Online Access:http://eprints.uthm.edu.my/2277/1/24p%20MOHD%20KHAIRUDDIN%20MAT%20YAMIN.pdf
http://eprints.uthm.edu.my/2277/2/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20COPYRIGHT%20DECLARATION.pdf
http://eprints.uthm.edu.my/2277/3/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20WATERMARK.pdf
http://eprints.uthm.edu.my/2277/
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.uthm.eprints.2277
record_format eprints
spelling my.uthm.eprints.22772021-10-31T05:08:31Z http://eprints.uthm.edu.my/2277/ Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability Mat Yamin, Mohd Khairuddin TK Electrical engineering. Electronics Nuclear engineering TK3001-3521 Distribution or transmission of electric power This project presents a methodological approach, suggestions and information in uprating the existing 275kV transmission overhead line. The work also calculate and analyses the effect of conductor swing angle on L3 tower top geometrics and keep the probability of flashover at low state. In this project, the insulator length and clearances of swing conductor to tower body, top cross-arm, bottom cross-arm and conductor to conductor are considered. The purpose of this work is to determine the clearances necessary to insulator withstand for 400kV line. In addition, it is also important to make sure that conductors have to maintain the clearances under TOV (temporary over-voltage), switching and lightning overvoltages. The work in this project have used Excel and Smart Draw to analyze the results and plot the clearance distances of swing conductor, also the phase to phase rms voltage and redrawing the existing overhead tower. Therefore, voltages rating for the L3 tower can be determined through the available clearances. Firstly, the voltage rating is determined with standard 400kV specification of insulator length. Then, the insulator is being shorted to do the analysis to the voltage rating and lastly, the overall cross-arm is changed to fully insulate such as composite cross-arm. As the result, by using standard insulator length, the tower only carried 351kV rather than composite cross-arm that carry 450kV. The standard L3 tower will be increase the power transfer capacity to 400kV in term of voltage by changing the steel cross-arm to composite cross-arm. 2012-07 Thesis NonPeerReviewed text en http://eprints.uthm.edu.my/2277/1/24p%20MOHD%20KHAIRUDDIN%20MAT%20YAMIN.pdf text en http://eprints.uthm.edu.my/2277/2/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20COPYRIGHT%20DECLARATION.pdf text en http://eprints.uthm.edu.my/2277/3/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20WATERMARK.pdf Mat Yamin, Mohd Khairuddin (2012) Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability. Masters thesis, Universiti Tun Hussein Onn Malaysia.
institution Universiti Tun Hussein Onn Malaysia
building UTHM Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Tun Hussein Onn Malaysia
content_source UTHM Institutional Repository
url_provider http://eprints.uthm.edu.my/
language English
English
English
topic TK Electrical engineering. Electronics Nuclear engineering
TK3001-3521 Distribution or transmission of electric power
spellingShingle TK Electrical engineering. Electronics Nuclear engineering
TK3001-3521 Distribution or transmission of electric power
Mat Yamin, Mohd Khairuddin
Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
description This project presents a methodological approach, suggestions and information in uprating the existing 275kV transmission overhead line. The work also calculate and analyses the effect of conductor swing angle on L3 tower top geometrics and keep the probability of flashover at low state. In this project, the insulator length and clearances of swing conductor to tower body, top cross-arm, bottom cross-arm and conductor to conductor are considered. The purpose of this work is to determine the clearances necessary to insulator withstand for 400kV line. In addition, it is also important to make sure that conductors have to maintain the clearances under TOV (temporary over-voltage), switching and lightning overvoltages. The work in this project have used Excel and Smart Draw to analyze the results and plot the clearance distances of swing conductor, also the phase to phase rms voltage and redrawing the existing overhead tower. Therefore, voltages rating for the L3 tower can be determined through the available clearances. Firstly, the voltage rating is determined with standard 400kV specification of insulator length. Then, the insulator is being shorted to do the analysis to the voltage rating and lastly, the overall cross-arm is changed to fully insulate such as composite cross-arm. As the result, by using standard insulator length, the tower only carried 351kV rather than composite cross-arm that carry 450kV. The standard L3 tower will be increase the power transfer capacity to 400kV in term of voltage by changing the steel cross-arm to composite cross-arm.
format Thesis
author Mat Yamin, Mohd Khairuddin
author_facet Mat Yamin, Mohd Khairuddin
author_sort Mat Yamin, Mohd Khairuddin
title Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
title_short Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
title_full Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
title_fullStr Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
title_full_unstemmed Voltage uprating of existing 275kV overhead transmission line tower for increasing the power transfer capability
title_sort voltage uprating of existing 275kv overhead transmission line tower for increasing the power transfer capability
publishDate 2012
url http://eprints.uthm.edu.my/2277/1/24p%20MOHD%20KHAIRUDDIN%20MAT%20YAMIN.pdf
http://eprints.uthm.edu.my/2277/2/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20COPYRIGHT%20DECLARATION.pdf
http://eprints.uthm.edu.my/2277/3/MOHD%20KHAIRUDDIN%20MAT%20YAMIN%20WATERMARK.pdf
http://eprints.uthm.edu.my/2277/
_version_ 1738580969735061504
score 13.188404