Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal
Construction and demolition (C&D) waste is resulting from the construction, renovation or demolition of building structures. C&D waste will increase from time to time in proportion to the development of a town or country. Specifically, this study would be more on renovation activities...
Saved in:
Main Author: | |
---|---|
Format: | Monograph |
Language: | English |
Published: |
Universiti Sains Malaysia
2006
|
Subjects: | |
Online Access: | http://eprints.usm.my/58244/1/Estimating%20Renovation%20Waste%20And%20Its%20Management%20In%20Seberang%20Perai%20Selatan%20A%20Case%20Study%20In%20Nibong%20Tebal_Muhamad%20Faizal%20Zainul.pdf http://eprints.usm.my/58244/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my.usm.eprints.58244 |
---|---|
record_format |
eprints |
spelling |
my.usm.eprints.58244 http://eprints.usm.my/58244/ Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal Zainul, Muhamad Faizal T Technology TA Engineering (General). Civil engineering (General) Construction and demolition (C&D) waste is resulting from the construction, renovation or demolition of building structures. C&D waste will increase from time to time in proportion to the development of a town or country. Specifically, this study would be more on renovation activities around the area of Nibong Tebal housing schemes. A survey of 7 housing schemes throughout the area of Nibong Tebal was made from October 2005 until January 2006. In addition, in order to get the representative informations of waste handling and disposal, related information from Majlis Perbandaran Seberang Perai (MPSP) and Pulau Burung Sanitary Landfill were also considered. The total amount of waste generated regarding to renovation activity for all the housing schemes is about 49.64m3 .These amount of waste required 6 number of lorries (10 tonnes) to evacuate the waste which composed of 66 percent concrete and bricks, 15 percent of other wastes, 14 percent of woods and the other 5 percent is for steel and aluminum waste. Thus, the necessity of finding appropriate management and solution to C&D waste destination must be reliable and clear so that the waste is well managed. Universiti Sains Malaysia 2006-05-01 Monograph NonPeerReviewed application/pdf en http://eprints.usm.my/58244/1/Estimating%20Renovation%20Waste%20And%20Its%20Management%20In%20Seberang%20Perai%20Selatan%20A%20Case%20Study%20In%20Nibong%20Tebal_Muhamad%20Faizal%20Zainul.pdf Zainul, Muhamad Faizal (2006) Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal. Project Report. Universiti Sains Malaysia, Pusat Pengajian Kejuruteraan Awam. (Submitted) |
institution |
Universiti Sains Malaysia |
building |
Hamzah Sendut Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Sains Malaysia |
content_source |
USM Institutional Repository |
url_provider |
http://eprints.usm.my/ |
language |
English |
topic |
T Technology TA Engineering (General). Civil engineering (General) |
spellingShingle |
T Technology TA Engineering (General). Civil engineering (General) Zainul, Muhamad Faizal Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
description |
Construction and demolition (C&D) waste is resulting from the construction,
renovation or demolition of building structures. C&D waste will increase from time to
time in proportion to the development of a town or country. Specifically, this study
would be more on renovation activities around the area of Nibong Tebal housing
schemes. A survey of 7 housing schemes throughout the area of Nibong Tebal was
made from October 2005 until January 2006. In addition, in order to get the
representative informations of waste handling and disposal, related information from
Majlis Perbandaran Seberang Perai (MPSP) and Pulau Burung Sanitary Landfill were
also considered. The total amount of waste generated regarding to renovation activity
for all the housing schemes is about 49.64m3
.These amount of waste required 6
number of lorries (10 tonnes) to evacuate the waste which composed of 66 percent
concrete and bricks, 15 percent of other wastes, 14 percent of woods and the other 5
percent is for steel and aluminum waste. Thus, the necessity of finding appropriate
management and solution to C&D waste destination must be reliable and clear so that
the waste is well managed. |
format |
Monograph |
author |
Zainul, Muhamad Faizal |
author_facet |
Zainul, Muhamad Faizal |
author_sort |
Zainul, Muhamad Faizal |
title |
Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
title_short |
Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
title_full |
Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
title_fullStr |
Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
title_full_unstemmed |
Estimating Renovation Waste And Its Management In Seberang Perai Selatan A Case Study In Nibong Tebal |
title_sort |
estimating renovation waste and its management in seberang perai selatan a case study in nibong tebal |
publisher |
Universiti Sains Malaysia |
publishDate |
2006 |
url |
http://eprints.usm.my/58244/1/Estimating%20Renovation%20Waste%20And%20Its%20Management%20In%20Seberang%20Perai%20Selatan%20A%20Case%20Study%20In%20Nibong%20Tebal_Muhamad%20Faizal%20Zainul.pdf http://eprints.usm.my/58244/ |
_version_ |
1765297667719561216 |
score |
13.160551 |