Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project
Al-Krama drinking water treatment plant has been playing a vital role in supplying drinking water to Baghdad city since 1980s. It was designed with a design capacity 22500 m3/d so that it can cover the needs of the public properly. However, the fatal circumstances which have recently hit Baghdad cit...
Saved in:
Main Authors: | , , |
---|---|
Other Authors: | |
Format: | Article |
Published: |
2023
|
Subjects: | |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my.uniten.dspace-30322 |
---|---|
record_format |
dspace |
spelling |
my.uniten.dspace-303222023-12-29T15:46:40Z Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project Mohammed A.A. Shaker S.A. Shakir A.A. 55539878000 31767661500 55539855100 Performance assessment Performance indicators Sustainability water treatment drinking plant Al-Krama drinking water treatment plant has been playing a vital role in supplying drinking water to Baghdad city since 1980s. It was designed with a design capacity 22500 m3/d so that it can cover the needs of the public properly. However, the fatal circumstances which have recently hit Baghdad city represented by wars and terrorist operations have considerably resulted in a significant deterioration in the quality of Al- Krama water treatment plant in the early of 2005s and 2006s. Furthermore, the failure of the equipments and the deficiency of the crew of the power plant have dramatically caused a shortage in the efficiency of the plant. Therefore, this work is the earliest attempt in addressing the problem of this plant. In this study, the removal efficient of the filtration, sedimentation will be addressed as well as the turbidity during three years of investigation. It was found that the average value of the removal of the sedimentation basin was about 24% which is obviously low due to the absence of the permanent maintenance and the continuous clean out for the sedimentation basin. The removal efficiency of filtration basin was as high as 85% comparatively with the removal efficiency of the sedimentation basin.The turbidity magnitudes were slightly oscillated along the study period since there has been shortage in the efficiency of sedimentation basin; it is then peaked at rainy season with about 20 NTU. The free chloride (CL2) was high but it may fall within the parameters, it is interesting to note that it was highly increased at September and December due to the high turbidity discharge. Final 2023-12-29T07:46:40Z 2023-12-29T07:46:40Z 2012 Article 2-s2.0-84871703678 https://www.scopus.com/inward/record.uri?eid=2-s2.0-84871703678&partnerID=40&md5=d80f77fee2d25afc7e9c31a759cbf3e9 https://irepository.uniten.edu.my/handle/123456789/30322 6 9 510 516 Scopus |
institution |
Universiti Tenaga Nasional |
building |
UNITEN Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Tenaga Nasional |
content_source |
UNITEN Institutional Repository |
url_provider |
http://dspace.uniten.edu.my/ |
topic |
Performance assessment Performance indicators Sustainability water treatment drinking plant |
spellingShingle |
Performance assessment Performance indicators Sustainability water treatment drinking plant Mohammed A.A. Shaker S.A. Shakir A.A. Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
description |
Al-Krama drinking water treatment plant has been playing a vital role in supplying drinking water to Baghdad city since 1980s. It was designed with a design capacity 22500 m3/d so that it can cover the needs of the public properly. However, the fatal circumstances which have recently hit Baghdad city represented by wars and terrorist operations have considerably resulted in a significant deterioration in the quality of Al- Krama water treatment plant in the early of 2005s and 2006s. Furthermore, the failure of the equipments and the deficiency of the crew of the power plant have dramatically caused a shortage in the efficiency of the plant. Therefore, this work is the earliest attempt in addressing the problem of this plant. In this study, the removal efficient of the filtration, sedimentation will be addressed as well as the turbidity during three years of investigation. It was found that the average value of the removal of the sedimentation basin was about 24% which is obviously low due to the absence of the permanent maintenance and the continuous clean out for the sedimentation basin. The removal efficiency of filtration basin was as high as 85% comparatively with the removal efficiency of the sedimentation basin.The turbidity magnitudes were slightly oscillated along the study period since there has been shortage in the efficiency of sedimentation basin; it is then peaked at rainy season with about 20 NTU. The free chloride (CL2) was high but it may fall within the parameters, it is interesting to note that it was highly increased at September and December due to the high turbidity discharge. |
author2 |
55539878000 |
author_facet |
55539878000 Mohammed A.A. Shaker S.A. Shakir A.A. |
format |
Article |
author |
Mohammed A.A. Shaker S.A. Shakir A.A. |
author_sort |
Mohammed A.A. |
title |
Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
title_short |
Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
title_full |
Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
title_fullStr |
Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
title_full_unstemmed |
Sustainability and performance evaluation of drinking water treatment plants: A case study in iraq of Al-Krama project |
title_sort |
sustainability and performance evaluation of drinking water treatment plants: a case study in iraq of al-krama project |
publishDate |
2023 |
_version_ |
1806428182283288576 |
score |
13.214268 |