Critical project management success factors analysis for the construction industry of Bangladesh

Purpose – This paper aims to identify the critical project management success factors and analyze those factors to achieve a sustainable construction industry in Bangladesh. Design/methodology/approach – This study identified 41 major problematic factors from the related literature. In this researc...

Full description

Saved in:
Bibliographic Details
Main Authors: Shuvo Dip Datta, Datta, Md. Habibur Rahman, Sobuz, Mohammad Nafe, Assafi, Norsuzailina, Mohamed Sutan, Md. Nazrul, Islam, Maria, Mannan, Abu Sayed, Mohammad Akid, Noor Md. Sadiqul, Hasan
Format: Article
Language:English
Published: Emerald Publishing Limited 2023
Subjects:
Online Access:http://ir.unimas.my/id/eprint/42001/3/Critical.pdf
http://ir.unimas.my/id/eprint/42001/
https://www.emerald.com/insight/content/doi/10.1108/IJBPA-01-2022-0006/full/html
https://doi.org/10.1108/IJBPA-01-2022-0006
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.unimas.ir.42001
record_format eprints
spelling my.unimas.ir.420012023-08-30T02:16:41Z http://ir.unimas.my/id/eprint/42001/ Critical project management success factors analysis for the construction industry of Bangladesh Shuvo Dip Datta, Datta Md. Habibur Rahman, Sobuz Mohammad Nafe, Assafi Norsuzailina, Mohamed Sutan Md. Nazrul, Islam Maria, Mannan Abu Sayed, Mohammad Akid Noor Md. Sadiqul, Hasan TA Engineering (General). Civil engineering (General) TH Building construction Purpose – This paper aims to identify the critical project management success factors and analyze those factors to achieve a sustainable construction industry in Bangladesh. Design/methodology/approach – This study identified 41 major problematic factors from the related literature. In this research, a detailed questionnaire survey was conducted among the experts and stakeholders of the construction industry of Bangladesh. The survey was carried out on a Likert scale and ranked the critical factors using the relative importance index (RII). The 41 problematic factors were divided into five group factors and ranked by the RII index to prioritize the factors. Finally, stakeholders’ opinions were analyzed with the critical assessed factors, which was a very effective technique to eliminate the risks and uncertain occurrences in the construction industry of Bangladesh. Findings – The factors analysis revealed that cost overrun, traffic jam, low wedges, slow payment for completed works and financial issues of the owner were leading critical factors in construction projects. Moreover, the critical factors are divided into five-factor groups, namely, financial management, monitoring and feedback, competency management, communication and coordination management, and risk management, which exhibit 0.767, 0.720, 0.711, 0.710 and 0.658 RII values. After all, the stakeholders’ opinion suggested that implementing modern tools and techniques can help to avoid the critical situation in the construction industry of Bangladesh. Practical implications – The construction industry of Bangladesh is moving away from stable construction work day by day. Previously, the potential CSFs were discussed unstructured way. Hence, detecting early warning signals in a structured way has become necessary for the building firm’s survival. Originality/value – Though some scattered critical issues are discussed in different literature, the critical issues of the Bangladeshi construction industry were not investigated extensively. Therefore, this study finds out the potential critical issues of the construction industry of Bangladesh to accumulate such harmful construction issues in a single platform so that the construction industry can have an overview of them with the help of innovative technologies. Emerald Publishing Limited 2023-01 Article PeerReviewed text en http://ir.unimas.my/id/eprint/42001/3/Critical.pdf Shuvo Dip Datta, Datta and Md. Habibur Rahman, Sobuz and Mohammad Nafe, Assafi and Norsuzailina, Mohamed Sutan and Md. Nazrul, Islam and Maria, Mannan and Abu Sayed, Mohammad Akid and Noor Md. Sadiqul, Hasan (2023) Critical project management success factors analysis for the construction industry of Bangladesh. International Journal of Building Pathology and Adaptation. pp. 1-30. ISSN 2398-4708 https://www.emerald.com/insight/content/doi/10.1108/IJBPA-01-2022-0006/full/html https://doi.org/10.1108/IJBPA-01-2022-0006
institution Universiti Malaysia Sarawak
building Centre for Academic Information Services (CAIS)
collection Institutional Repository
continent Asia
country Malaysia
content_provider Universiti Malaysia Sarawak
content_source UNIMAS Institutional Repository
url_provider http://ir.unimas.my/
language English
topic TA Engineering (General). Civil engineering (General)
TH Building construction
spellingShingle TA Engineering (General). Civil engineering (General)
TH Building construction
Shuvo Dip Datta, Datta
Md. Habibur Rahman, Sobuz
Mohammad Nafe, Assafi
Norsuzailina, Mohamed Sutan
Md. Nazrul, Islam
Maria, Mannan
Abu Sayed, Mohammad Akid
Noor Md. Sadiqul, Hasan
Critical project management success factors analysis for the construction industry of Bangladesh
description Purpose – This paper aims to identify the critical project management success factors and analyze those factors to achieve a sustainable construction industry in Bangladesh. Design/methodology/approach – This study identified 41 major problematic factors from the related literature. In this research, a detailed questionnaire survey was conducted among the experts and stakeholders of the construction industry of Bangladesh. The survey was carried out on a Likert scale and ranked the critical factors using the relative importance index (RII). The 41 problematic factors were divided into five group factors and ranked by the RII index to prioritize the factors. Finally, stakeholders’ opinions were analyzed with the critical assessed factors, which was a very effective technique to eliminate the risks and uncertain occurrences in the construction industry of Bangladesh. Findings – The factors analysis revealed that cost overrun, traffic jam, low wedges, slow payment for completed works and financial issues of the owner were leading critical factors in construction projects. Moreover, the critical factors are divided into five-factor groups, namely, financial management, monitoring and feedback, competency management, communication and coordination management, and risk management, which exhibit 0.767, 0.720, 0.711, 0.710 and 0.658 RII values. After all, the stakeholders’ opinion suggested that implementing modern tools and techniques can help to avoid the critical situation in the construction industry of Bangladesh. Practical implications – The construction industry of Bangladesh is moving away from stable construction work day by day. Previously, the potential CSFs were discussed unstructured way. Hence, detecting early warning signals in a structured way has become necessary for the building firm’s survival. Originality/value – Though some scattered critical issues are discussed in different literature, the critical issues of the Bangladeshi construction industry were not investigated extensively. Therefore, this study finds out the potential critical issues of the construction industry of Bangladesh to accumulate such harmful construction issues in a single platform so that the construction industry can have an overview of them with the help of innovative technologies.
format Article
author Shuvo Dip Datta, Datta
Md. Habibur Rahman, Sobuz
Mohammad Nafe, Assafi
Norsuzailina, Mohamed Sutan
Md. Nazrul, Islam
Maria, Mannan
Abu Sayed, Mohammad Akid
Noor Md. Sadiqul, Hasan
author_facet Shuvo Dip Datta, Datta
Md. Habibur Rahman, Sobuz
Mohammad Nafe, Assafi
Norsuzailina, Mohamed Sutan
Md. Nazrul, Islam
Maria, Mannan
Abu Sayed, Mohammad Akid
Noor Md. Sadiqul, Hasan
author_sort Shuvo Dip Datta, Datta
title Critical project management success factors analysis for the construction industry of Bangladesh
title_short Critical project management success factors analysis for the construction industry of Bangladesh
title_full Critical project management success factors analysis for the construction industry of Bangladesh
title_fullStr Critical project management success factors analysis for the construction industry of Bangladesh
title_full_unstemmed Critical project management success factors analysis for the construction industry of Bangladesh
title_sort critical project management success factors analysis for the construction industry of bangladesh
publisher Emerald Publishing Limited
publishDate 2023
url http://ir.unimas.my/id/eprint/42001/3/Critical.pdf
http://ir.unimas.my/id/eprint/42001/
https://www.emerald.com/insight/content/doi/10.1108/IJBPA-01-2022-0006/full/html
https://doi.org/10.1108/IJBPA-01-2022-0006
_version_ 1775627322742800384
score 13.159267