A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network
The growing of Photovoltaic (PV) power generation and integration into the electric power has started to touch on the stability and reliability of the network. As a result, standards have to be defined in guaranteeing a secure and reliable operation of the power system and one of the important topic...
Saved in:
Main Authors: | , , |
---|---|
Format: | Conference or Workshop Item |
Language: | English English |
Published: |
2015
|
Subjects: | |
Online Access: | http://umpir.ump.edu.my/id/eprint/11525/1/A%20Review%20of%20the%20Fault%20Ride%20Through%20Requirements%20In%20Different%20Grid%20Codes%20Concerning%20Penetration%20of%20PV%20System%20to%20the%20Electric%20Power%20Network.pdf http://umpir.ump.edu.my/id/eprint/11525/7/fkee-al-shetwi%2C%20ali%20q.-a%20review%20of%20the%20fault%20ride.pdf http://umpir.ump.edu.my/id/eprint/11525/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my.ump.umpir.11525 |
---|---|
record_format |
eprints |
spelling |
my.ump.umpir.115252019-10-18T02:41:18Z http://umpir.ump.edu.my/id/eprint/11525/ A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network Al-Shetwi, Ali Q. Muhamad Zahim, Sujod Noor Lina, Ramli TK Electrical engineering. Electronics Nuclear engineering The growing of Photovoltaic (PV) power generation and integration into the electric power has started to touch on the stability and reliability of the network. As a result, standards have to be defined in guaranteeing a secure and reliable operation of the power system and one of the important topics is the capability of the PV system to ride through fault during the disturbance. This paper provides an overview and comparison study about Fault Ride-Through (FRT) capability requirements in the recent grid codes, which are enforced by transmission and distribution system operators in different Grid Codes (GCs) regarding the penetration of Photovoltaic Power Plant (PVPP) to medium and low voltage level of the network. This study compared the following common requirements such as FRT either Low Voltage Ride-Through (LVRT) or High Voltage Ride Through (HVRT), reactive current injection during and after the fault, restoring active power and frequency variations. In addition, by depending on this comparison and through studying the Malaysian grid standards, there is a similarity to USA standard thus this paper presents a proposal of FRT capability and frequency deviation for the Malaysian electric grid. 2015 Conference or Workshop Item PeerReviewed application/pdf en http://umpir.ump.edu.my/id/eprint/11525/1/A%20Review%20of%20the%20Fault%20Ride%20Through%20Requirements%20In%20Different%20Grid%20Codes%20Concerning%20Penetration%20of%20PV%20System%20to%20the%20Electric%20Power%20Network.pdf application/pdf en http://umpir.ump.edu.my/id/eprint/11525/7/fkee-al-shetwi%2C%20ali%20q.-a%20review%20of%20the%20fault%20ride.pdf Al-Shetwi, Ali Q. and Muhamad Zahim, Sujod and Noor Lina, Ramli (2015) A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network. In: International Conference on Electrical Control and Computer Engineering 2015, 27-28 October 2015 , Kuantan, Pahang. pp. 1-6.. (Unpublished) |
institution |
Universiti Malaysia Pahang |
building |
UMP Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Malaysia Pahang |
content_source |
UMP Institutional Repository |
url_provider |
http://umpir.ump.edu.my/ |
language |
English English |
topic |
TK Electrical engineering. Electronics Nuclear engineering |
spellingShingle |
TK Electrical engineering. Electronics Nuclear engineering Al-Shetwi, Ali Q. Muhamad Zahim, Sujod Noor Lina, Ramli A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
description |
The growing of Photovoltaic (PV) power generation and integration into the electric power has started to touch on the stability and reliability of the network. As a result, standards have to be defined in guaranteeing a secure and reliable operation of the power system and one of the important topics is the capability of the PV system to ride through fault during the disturbance. This paper provides an overview and comparison study about Fault Ride-Through (FRT) capability requirements in the recent grid codes, which are enforced by transmission and distribution system operators in different Grid Codes (GCs) regarding the penetration of Photovoltaic Power Plant (PVPP) to medium and low voltage level of the network. This study compared the following common requirements such as FRT either Low Voltage Ride-Through (LVRT) or High Voltage Ride Through (HVRT), reactive current injection during and after the fault, restoring active power and frequency variations. In addition, by depending on this comparison and through studying the Malaysian grid standards, there is a similarity to USA standard thus this paper presents a proposal of FRT capability and frequency deviation for the Malaysian electric grid. |
format |
Conference or Workshop Item |
author |
Al-Shetwi, Ali Q. Muhamad Zahim, Sujod Noor Lina, Ramli |
author_facet |
Al-Shetwi, Ali Q. Muhamad Zahim, Sujod Noor Lina, Ramli |
author_sort |
Al-Shetwi, Ali Q. |
title |
A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
title_short |
A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
title_full |
A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
title_fullStr |
A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
title_full_unstemmed |
A Review of the Fault Ride Through Requirements in Different Grid Codes Concerning Penetration of PV System to the Electric Power Network |
title_sort |
review of the fault ride through requirements in different grid codes concerning penetration of pv system to the electric power network |
publishDate |
2015 |
url |
http://umpir.ump.edu.my/id/eprint/11525/1/A%20Review%20of%20the%20Fault%20Ride%20Through%20Requirements%20In%20Different%20Grid%20Codes%20Concerning%20Penetration%20of%20PV%20System%20to%20the%20Electric%20Power%20Network.pdf http://umpir.ump.edu.my/id/eprint/11525/7/fkee-al-shetwi%2C%20ali%20q.-a%20review%20of%20the%20fault%20ride.pdf http://umpir.ump.edu.my/id/eprint/11525/ |
_version_ |
1648741070797799424 |
score |
13.211869 |