Late payment issues of subcontractors in Malaysian construction industry

The practice of efficient and timely payment in construction projects is a major factor that can contribute to the success of a project. Delays in payment to subcontractor(s) by main contractor and client on construction projects in the Malaysian construction industry is considered to be a significa...

Full description

Saved in:
Bibliographic Details
Main Authors: Che Haron, Roziha, Arazmi, Ahmad Lutfil
Format: Article
Language:English
English
Published: Malaysian Institute Of Planners 2020
Subjects:
Online Access:http://irep.iium.edu.my/80347/1/80347_Late%20payment%20issues%20of%20subcontractors.pdf
http://irep.iium.edu.my/80347/2/80347_Late%20payment%20issues%20of%20subcontractors_SCOPUS.pdf
http://irep.iium.edu.my/80347/
http://www.planningmalaysia.org/index.php/pmj/article/view/711/540
Tags: Add Tag
No Tags, Be the first to tag this record!
id my.iium.irep.80347
record_format dspace
spelling my.iium.irep.803472021-01-20T15:25:59Z http://irep.iium.edu.my/80347/ Late payment issues of subcontractors in Malaysian construction industry Che Haron, Roziha Arazmi, Ahmad Lutfil NA Architecture The practice of efficient and timely payment in construction projects is a major factor that can contribute to the success of a project. Delays in payment to subcontractor(s) by main contractor and client on construction projects in the Malaysian construction industry is considered to be a significant factor of concern. It causes severe cash flow problems to subcontractor(s) and this condition may lead to a devastating impact to the contractual payment chain. Withholding or delaying payment creates financial hardship for the construction companies and its impacts are sometimes so harsh that some companies have to close down their services. The research methodology adopted was the questionnaire survey analysis based on thirty (37) respondents from selected main contractors and sub-contractors in Gombak, Selangor. The data and information were also gathered from interviews analysis. From the research findings, among the factor of late payment from the client is payment withhold by the client. Meanwhile, the factor of late payment from the main contractor is when the term of “pay when paid” is applied. To improve the payment situation, the findings of this study suggest that there must be dedicated enforcing provisions for payment delay in contracts. This is proposed by introducing the standard form of contract clause regarding payment between the main contractor and domestic subcontractor which include levying charges on overdue payments. Malaysian Institute Of Planners 2020-04-09 Article PeerReviewed application/pdf en http://irep.iium.edu.my/80347/1/80347_Late%20payment%20issues%20of%20subcontractors.pdf application/pdf en http://irep.iium.edu.my/80347/2/80347_Late%20payment%20issues%20of%20subcontractors_SCOPUS.pdf Che Haron, Roziha and Arazmi, Ahmad Lutfil (2020) Late payment issues of subcontractors in Malaysian construction industry. Planning Malaysia, 18 (1). pp. 78-91. ISSN 1675-6215 E-ISSN 0128-0945 http://www.planningmalaysia.org/index.php/pmj/article/view/711/540
institution Universiti Islam Antarabangsa Malaysia
building IIUM Library
collection Institutional Repository
continent Asia
country Malaysia
content_provider International Islamic University Malaysia
content_source IIUM Repository (IREP)
url_provider http://irep.iium.edu.my/
language English
English
topic NA Architecture
spellingShingle NA Architecture
Che Haron, Roziha
Arazmi, Ahmad Lutfil
Late payment issues of subcontractors in Malaysian construction industry
description The practice of efficient and timely payment in construction projects is a major factor that can contribute to the success of a project. Delays in payment to subcontractor(s) by main contractor and client on construction projects in the Malaysian construction industry is considered to be a significant factor of concern. It causes severe cash flow problems to subcontractor(s) and this condition may lead to a devastating impact to the contractual payment chain. Withholding or delaying payment creates financial hardship for the construction companies and its impacts are sometimes so harsh that some companies have to close down their services. The research methodology adopted was the questionnaire survey analysis based on thirty (37) respondents from selected main contractors and sub-contractors in Gombak, Selangor. The data and information were also gathered from interviews analysis. From the research findings, among the factor of late payment from the client is payment withhold by the client. Meanwhile, the factor of late payment from the main contractor is when the term of “pay when paid” is applied. To improve the payment situation, the findings of this study suggest that there must be dedicated enforcing provisions for payment delay in contracts. This is proposed by introducing the standard form of contract clause regarding payment between the main contractor and domestic subcontractor which include levying charges on overdue payments.
format Article
author Che Haron, Roziha
Arazmi, Ahmad Lutfil
author_facet Che Haron, Roziha
Arazmi, Ahmad Lutfil
author_sort Che Haron, Roziha
title Late payment issues of subcontractors in Malaysian construction industry
title_short Late payment issues of subcontractors in Malaysian construction industry
title_full Late payment issues of subcontractors in Malaysian construction industry
title_fullStr Late payment issues of subcontractors in Malaysian construction industry
title_full_unstemmed Late payment issues of subcontractors in Malaysian construction industry
title_sort late payment issues of subcontractors in malaysian construction industry
publisher Malaysian Institute Of Planners
publishDate 2020
url http://irep.iium.edu.my/80347/1/80347_Late%20payment%20issues%20of%20subcontractors.pdf
http://irep.iium.edu.my/80347/2/80347_Late%20payment%20issues%20of%20subcontractors_SCOPUS.pdf
http://irep.iium.edu.my/80347/
http://www.planningmalaysia.org/index.php/pmj/article/view/711/540
_version_ 1690370720935182336
score 13.18916